Project Overview


The City of Lake Forest Park will be constructing a roundabout on Ballinger Way NE at the intersection of SR-104, 40th Place NE, and NE 184th Street. Construction will begin in the first half of 2025. This new roundabout will include a single-lane roundabout, new sidewalks, shared-use pathways, four pedestrian crossings with refuge islands, and improved street lighting.

With a focus on safety, efficiency, and environmental sustainability, this project will allow our community to grow mindfully while also improving air quality and providing the essential infrastructure needed to promote non-vehicular travel along the SR-104 corridor.

Timeline                      Spring 2026 - Winter 2027
Project Status            Pre-Construction
Project Cost               $8.6 Million

What to Expect

Construction is anticipated to begin in the first half of 2026 and be completed end of 2027. Throughout the construction period, work will alternately occur on the northbound and southbound sections of SR-104, resulting in reduced traffic lanes managed by a flagger.

Timing for all closures and partial closures is yet to be determined. Stay tuned for posted notices and updates on our website during the construction period.

Neighborhood Meeting Presentation from November 6, 2025


For residents who were unable to attend the Neighborhood Meeting regarding the SR 104 Roundabout at 40th Place NE project, the full presentation is available for download in PDF format here. It should be noted, that due to numerous public comments/questions, the presentation was truncated at page 17 during the formal presentation.

Roundabout at SR-104, 40th PL NE & NE 184th St 

Tabbed Content
History & Background
Timeline
Funding
Contact
The need for safety improvements at this intersection was first documented in the City’s 2017 Safe Highways Planning Context Report, with the proposal to construct a roundabout introduced in the 2018 Safe Highways Report. Between 2015 and 2018, the report noted thirteen collisions, and since its publication, additional collisions, including near misses, have continued to occur. This project aims to enhance safety at the intersection of SR 104, 40th Place NE, and NE 184th Street while also improving efficiency along the broader SR 104 corridor.
  • June 2025 Project Advertised
  • September 2025 Contract Awarded
  • Early 2026 Construction Scheduled to Begin
  • Late 2027 Construction Scheduled for Completion
This project is funded by grants from the Washington State Transportation Improvement Board and the Washington State Department of Transportation, as well as a loan from the Washington State Department of Commerce Public Works Board and City funding. The total projected cost is $8.6 million.